Reduction of Frame Body boring bar change over time for 6 models thru SMED

02_2_2011AwardImage

Project initiation date: 20.10.10

Challenge

Weld shop Machine wise production data collect Last six month Avg. (Mar-Aug-10) Fine Boring production is less (25/Shift) then other Machine’s

Figure 1Hero 20112